Aker Solutions wins contract for Norwegian Sea tie-back job

Energy Disrupter

Fossil Energy – Tie Back

Equinor has awarded Aker Solutions with a contract to tie back two gas fields in the Norwegian Sea to the Åsgard B platform.

The Berling tie-in to Åsgard B is an EPCIC project comprising engineering, procurement, construction, installation and commissioning. 

Berling is located on the Halten Bank in the Norwegian Sea about 23 kilometers south-east of the Åsgard field.

Two EPCIC scopes define the project: the first starts immediately, and the second in September 2023. Offshore mobilization will begin in November 2025, and the tie-back is to be completed in December 2027. Production start is planned to 2028, Aker Solutions said.

Construction and prefabrication will be executed at the company’s yard in Egersund.

Original Source: https://ocean-energyresources.com/2023/03/28/aker-solutions-wins-contract-for-norwegian-sea-tie-back-job/