Sandbank SOV service campaign 2024 successfully completed

Energy Disrupter

Wind Energy – Sandbank

Brian Stuhr, Operations & Maintenance Manager Sandbank mentioned in a social media post the successful completion of the Sandbank SOV service campaign 2024.

Photo courtesy: Sandbank.

After 10 weeks with the Acta Centaurus the Sandbank team managed to complete the WTG, Statutory and Foundation Service Campaign on all 72 turbines – 13 days ahead of schedule.  

In order to achieve this, 40 technicians in 8 teams completed 29000 working hours on the turbines.  

The Acta Centaurus is now at DanTysk with another 80 turbines waiting for their service.