Jacket Hollandse Kust Noord installed
WInd energy – TenneT
The jacket foundation for the Hollandse Kust Noord offshore substation has been installed off the northern coast of the Netherlands.
The topside for this 700 MW offshore substation is scheduled to be installed in May 2022, the transmission system operator TenneT says in a press release.
After departing from the port of Vlissingen, the jacket arrived at its destination more than 18 kilometers off the coast of Egmond in 20 hours. After exact positioning on-site, the 2,100-ton steel construction was placed on the seabed by a heavy-lift vessel.
Original Source: https://ocean-energyresources.com/2021/11/12/jacket-hollandse-kust-noord-installed/