Living Stone starts installation inter-array cables Moray East
DEME Offshore’s cable laying vessel Living Stone has started the first inter-array cable installation campaign at the 950 MW Moray East wind farm offshore Scotland.
The wind farm will feature 100 66 kV inter-array cables and two offshore substation interconnector cables supplied by JDR Cable System.
The installation campaign will be carried out in three phases. The first campaign started at the end of September and will continue for eight weeks.
DEME Offshore is also the EPCI contractor for the wind farm’s turbine foundations and three offshore substation foundations, as well as for the transport and installation of the OTMs.